Project introduction
National plan for desalination and water transfer from the coasts of Chabahar to the eastern provinces of the country
(simultaneous production of water and electricity)
Project goals
Eliminate the problem of shortage of drinking water, as well as the water needed for industry and agriculture in the east of the country from sustainable water resources (unconventional waters of the south of the country “Oman Sea” and pay special attention to the development of industry and mining in the eastern provinces.
- Activate and make use ofthe potentials of the private sector.
- To rely on local capacities through the construction of power plants and water desalination using modern technology and with the aim of localization and transmission of fresh water and electricity needed for high-yield industry and agriculture
- To create job and make use of the capacities and potentialities of local people, as well as the involvement of the private sector
- To create a very valuable opportunity to access ocean waters through the Chabahar Free Zone, as well as creating infrastructure for water and electricity in the east of the country.
- Increase energy production efficiency (above 80%).
- Creating a suitable situation for activating the mining industry in the eastern corridor of the country, considering the creation of appropriate infrastructure and enthusiasm for private sector investors.
- Maintanance of sustainable security in the east of the country through job creation, wealth creation, population stabilization in the eastern part of the country.
Technical specifications of the project
Water extraction, desalination and power generation facilities: This project is under construction with the intention of producing desalinated water up to a capacity of 2,400,000 cubic meters per day (750 million cubic meters per year) near Chabahar city between Ramin and Kacho villages with the following specifications:
Offshore water extraction facilities with a capacity of saline water intake up to 7.2 million cubic meters per day, which is transferred to the intake structure by gravity from a distance of 1.3 km and a depth of 20 meters.
The first phase consists of 8 desalination facilities, each with a capacity of 100,000 cubic meters per day, which includes pre-treatment facilities, chemical injection, clarification unit with dissolved air flotation, two-layer filtration unit, desalination unit and energy recovery systems.
24 water storage tanks for fresh water storage and transfer to the pumping station, each with a capacity of one hundred thousand cubic meters.
The required power of desalination units in the first phase is equal to 210 MW.
Geographical area of the project:
The present project of water extraction and desalination plant is located near the village (Ramin) located in the east of Chabahar city. The water transfer system will start from the desalination facility and will respectively meet the water needs of the provinces along the route that passes through the provinces of Sistan and Baluchestan, South Khorasan and Khorasan Razavi
Identification of the national plan for desalination and water transfer from the coasts of Chabahar to the eastern provinces of the country |
---|
+Client: Takapoi Water and Electricity Company East of Chabahar Free Zone (Tabesh) +Consultant: Toos Ab Consulting Engineer Company |
Notification of the Ministry of Energy to the national plan for desalination and transfer of water from the shores of Chabahar to the eastern provinces of the country | ||||
---|---|---|---|---|
province | Sistan and Baluchestan | southern Khorasan | Khorasan Razavi | sum |
The amount of desalinated water according to the notified allocation (million cubic meters per year) | 100 | 60 | 120 | 280 |
Technical specifications of the system Water transfer of the first segment of the transmission line
The first segment starts from the desalination plant on the shores of Chabahar and extends to the city of Zahedan. The length of this segment is about 620 km and contains 11 pumping stations in this segment.
The share of desalinated water for Sistan and Baluchestan is 100 million cubic meters per year, including the use of the coastal strip and the internal consumption of the province.
Technical specifications of water transmission system The second segment of the transmission line
The second segment of the water transmission line starts from Zahedan city and after passing through Nehbandan, Sarbisheh, Birjand and Ghaen cities, extends to Gonabad region. The length of this section is 640 km and includes seven pumping stations.
The share of South Khorasan province in this line is 60 million cubic meters of desalinated water per year.
Technical specifications of the first segment (Chabahar - Iranshahr - Zahedan) | ||
---|---|---|
Description | Specifications | |
Length of pipe transmission line | 620 km | |
Transmission line diameter | 2200 mm | |
Transmission line material | Steel | |
Type of external and internal cover | Vapox three-layer polyethylene | |
Transmission line capacity | 280 million cubic meters per year | |
8.8 cubic meters per second | ||
Number of pumping stations | 11stations | |
Power required | 280 Mwats |
Technical specifications of water transmission system The third segment of the transmission line
This part of the water transmission line starts from Gonabad area and extends to the holy city of Mashhad after passing through the cities of Feyzabad and Torbat Heydariyeh. The length of this segment is 250 km and contains 5 pumping stations. The share of Khorasan Razavi province in this line is 120 million cubic meters of desalinated water per year.
Technical specifications of the third segment (Gonabad - Torbat Heydariyeh - Mashhad) | ||
---|---|---|
Description | Specifications | |
Length of pipe transmission line | 250 km | |
Transmission line diameter | 1600 mm | |
Transmission line material | Steel | |
Type of external and internal cover | Vapox three-layer polyethylene | |
Transmission line capacity | 120 million cubic meters per year | |
3.8 cubic meters per second | ||
Number of pumping stations | 5 stations | |
Power required | 40 Mwats | |
Maximum path height above sea level in this section | 2000 |
Initial phase of the project (water supply to Makran Industries)
The implementation of this phase with the intention of meeting part of the water needs of Chabahar Free Zone, including steel and heavy industries as an initial phase of the project, with a capacity of 100,000 cubic meters per day is on the agenda and includes the construction of part of the project From the location of the desalination plant to the location of the target industries and the construction of two power plants (each with a capacity of 25 MW).
Technical specifications of (Gonabad - Torbat Heydariyeh - Mashhad) | ||
---|---|---|
Description | Specifications | |
Length of pipe transmission line | 25 km | |
Transmission line diameter | 700 mm | |
Transmission line material | GRP | |
Capacity | 100,000 cubic meters per day | |
Number of pumping stations | 1 station | |
Power required | 50 Mwats |